DAY 4: NORTHERN SECTION OF THE ASSEMBLY CENTER — 25% COMPLETE

Hanoi, Vietnam • Hòa Lạc Hi-Tech Park • October 20

More details at the link: https://youtube.com/shorts/B_duS5FK8Ks?si=E7HBStxa_XnBxn0N


The corridor walls have been painted. Flooring, baseboards, and transition strips have been installed halfway in the northern section of the building.

The air conditioners have been adjusted.